PREPARATION OF THE DRAIN FOR CONNECTING

The body of the drain off ers ready (preformed) holes for subsequent connections.

The holes can be opened with a hammer but only if the grid is installed in the drain. This will prevent damage to the drain. After hammering out the opening it can be cleaned up with a fi le. You can use up to four side pre-prepared holes for the installation of pipes size DN 50. The Bottom hole can be opened in the same way. You can also connect sewer pipes size DN 110.

RECOMMENDATIONS FOR USE OF CONCRETE

Strength class is one of the basic parameters of concrete.

Concrete of ordinary strength grades are commonly available in concrete plants. Individual schemes set the parameters that the concrete must meet to be resistant to its immediate environment throughout its lifetime.

Strength
class
Type
ALCA
Classes
C12/15HOME
HOME+
A15
C20/25STANDARDB125
C30/37PROFIC250
C30/37TOPD400

AVZ101-R101

Instalace AVZ101-R101

Provide suffi cient space not only for the drain, but also for the required concrete bed.

Instalace AVZ101-R101

Choose the location of the outlet (lowest position), the beginning and end of the line. The minimum height of the concrete slab is 10 cm.

Instalace AVZ101-R101

Adjust the height so as to achieve a downward slope. Install the drains with the grids in them, to prevent deformation of the body during concrete hardening. To avoid the grids from getting dirty and contaminated, we recommend that you cover them in PVC foil.

Instalace AVZ101-R101

The surrounding surface should be permanently 3 – 5 mm above the top surface of the drain cover. In the case of concrete paving for frequently used surfaces, we recommend at least that the ones in areas close to the drain to be fixed into a concrete bed.

Instalace AVZ101-R101

AVZ102-R102

Instalace AVZ102-R102

Provide suffi cient space not only for the drain, but also for the required concrete bed.

Instalace AVZ102-R102

Choose the location of the outlet (lowest position), the beginning and end of the line. The minimum height of the concrete slab is 10 cm.

Instalace AVZ102-R102

Adjust the height so as to achieve a downward slope. Install the drains with the grids in them, to prevent deformation of the body during concrete hardening. To avoid the grids from getting dirty and contaminated, we recommend that you cover them in PVC foil.

Instalace AVZ102-R102

The surrounding surface should be permanently 3 – 5 mm above the top surface of the drain cover. In the case of concrete paving for frequently used surfaces, we recommend at least that the ones in areas close to the drain to be fixed into a concrete bed.

Instalace AVZ102-R102

AVZ102-R103

Instalace AVZ102-R103

Provide suffi cient space not only for the drain, but also for the required concrete bed.

Instalace AVZ102-R103

Choose the location of the outlet (lowest position), the beginning and end of the line. The minimum height of the concrete slab is 10 cm.

Instalace AVZ102-R103

Adjust the height so as to achieve a downward slope. Install the drains with the grids in them, to prevent deformation of the body during concrete hardening. To avoid the grids from getting dirty and contaminated, we recommend that you cover them in PVC foil.

Instalace AVZ102-R103

The surrounding surface should be permanently 3 – 5 mm above the top surface of the drain cover. In the case of concrete paving for frequently used surfaces we recommend to proceed according to the diagram below.

Instalace AVZ102-R103

AVZ103-R104

Instalace AVZ103-R104

Provide suffi cient space not only for the drain, but also for the required concrete bed.

Instalace AVZ103-R104

Choose the location of the outlet (lowest position), the beginning and end of the line. The minimum height of the concrete slab 15 cm. Into the concrete slab insert reinforcing steel Ø10 mm, every 40 cm.

Instalace AVZ103-R104

Adjust the height so as to achieve a downward slope. To avoid deformation during installation the drains come with, metal strips which, after concreting are to be removed.

Instalace AVZ103-R104

The surrounding surface should be permanently 3 – 5 mm above the top surface of the drain cover. The drain’s entire height must be cemented. Width (thickness) of the side of the concrete layer is recommended at least 15 cm.

Instalace AVZ103-R104

AVZ103-R201

Instalace AVZ103-R201

Provide suffi cient space not only for the drain, but also for the required concrete bed.

Instalace AVZ103-R201

Choose the location of the outlet (lowest position), the beginning and end of the line. The minimum height of the concrete slab is 20 cm. Into the concrete slab insert reinforcing steel Ø10 mm, every 40 cm.

Instalace AVZ103-R201

Adjust the height so as to achieve a downward slope. To avoid deformation during installation the drains come with, which, after concreting are to be removed.

Instalace AVZ103-R201

The surrounding surface should be permanently 3 – 5 mm above the top surface of the drain cover. The drain’s entire height must be cemented. Width (thickness) of the side of the concrete layer is recommended at least 20 cm.

Instalace AVZ103-R201